The line that serves South Bend in 2026 is publicly owned, newly double-tracked on its western half, and still arguing about where its eastern end should be: Since 31 March 2026, when the district opened its Monon Corridor — the eight-mile branch from Hammond Gateway to Munster and Dyer, the South Shore's first branch line, built as the West Lake Corridor — the original main line carries the name Lakeshore Corridor, South Bend to Chicago. The Monon Corridor is Lake County's ground and appears here only because it renamed this city's line; the record prints it as context, not as South Bend's. South Bend Airport service stands at six weekday round trips, as Railway Age counted them in 2025, the expresses carded at one hour forty-nine minutes to Millennium Station in Chicago.

The standing project is the terminus. The 1992 airport station sits on the airport's east side at the end of a circuitous approach; NICTD's own special-projects page states the plan plainly: the station will be moved from the terminal's east side to its west side, distance reduced, curves eliminated, grade crossings reduced — up to eighteen of them, on the project's engineering record — with the South Bend–Chicago time "substantially reduced to just ninety minutes" in conjunction with the line's other projects. The project's estimate stands at $112 million, with construction planned for 2026–2027; the design contract has been awarded to DLZ Indiana. The downtown alternative has its own long file: championed by Mayor Pete Buttigieg, studied in 2018 among five candidate sites, it remains — in the district's own position — a possible future addition even if the west-side airport station is built, and nothing in the present record funds it. South Bend's passenger geography thus stands exactly where the 1970 cutback left it: at the city's edge, with two separate plans — the South Shore's to the airport's west side, Amtrak's to Union Station — arguing, in studies, for something better.

Sources:

  1. NICTD, "Monon Corridor 101" and the South Shore Line's announcement — passenger service on the Monon Corridor officially began 31 March 2026; the main line's name henceforth the Lakeshore Corridor, South Bend to Chicago.
  2. NICTD, Special Projects page — the South Bend Airport Realignment: the station moved from the terminal's east side to its west side, distance, curves and grade crossings reduced, and South Bend–Chicago time "substantially reduced to just 90 minutes"; the New Carlisle station feasibility study alongside it.
  3. The Airport Realignment's project record — the $112 million estimate, construction planned 2026–2027, up to eighteen at-grade crossings eliminated, and the downtown terminus's history among the alternatives, including the 2018 five-site study.
  4. Railway Age, May 2025 — six weekday round trips serving South Bend Airport, and the line's present position: downtown gone since 1970, the airport terminus since 1992, a downtown return possible in the plans but a long shot at present.